Foundation walls and parkade nearing completion

DSC_0014_MV_VEXZOYJOXBEV DSC_0018_MV_NUZMSGZCWGQS DSC_0021_MV_QZWIIEYNQYIK DSC_0030_MV_VIRGQABXFRUL

The foundation walls and parkade of our new facility are nearing completion as we enter month three of our construction phase. The construction of the underground parkade is scheduled to be completed around Oct 21. Shortly thereafter attention will turn to the first level or ground floor of the building which should be completed by mid November. In mid November the crane will be installed on the site. After that each floor of both buildings will take shape roughly one floor per month until late March 2015 when the entire concrete exterior structure will be completed. Construction site meetings are now scheduled every two weeks to monitor the construction phase progress – site meeting #3 is happening tomorrow morning, Oct 8.